The objective of the PICOMB SME Instrument Phase 2 project is to gain market acceptance for this disruptive innovation through design, development, prototyping, customer trials, commercialisation and commercial partnership formation.

The sub-objectives that will enable us to achieve market acceptance are listed in Table 5 The successful outcome of the project will see a commercial partnership secured with at least one customer for our comb source technology, either to manufacture directly or to integrate it into their systems.

Table 5: PICOMB Phase 2 Objectives

Objectives Description Success criteria WP
Objective 1: Design Refinement
Sub-objective 1.1: Platform Research Research to finalise integration platform and fab provider. Current approach is monolithic InP. Integration platform chosen, design fundamentals chosen WP2
Sub-objective 1.2: Development of the Design Refine the design via modelling and CAD tools to meet customer requirements that have been provided. Models showing up to 8 channel source and demux PIC with 75GHz spacing and low linewidth WP2
Objective 2: Prototype Development
Sub-objective 2.1: Build Prototype Build a prototype including PIC, optical Package, Evaluation Board and Software for customers to trial. Prototype consisting of packaged PIC on evaluation board complete WP3
Sub-objective 2.2: Test Prototype Integrate and test prototype to ensure required specifications are met. Prototype meets customer requirements WP3
Objective 3: Customer Sampling
Sub-objective 3.1: Customer Trials Design and initiate technology trials several customers or end users. Multiple customer trials complete WP4
Objective 4: Partnership Agreement
Sub-objective 4.1: Commercial Partnership Agreement Following successful trials, negotiate partnership agreement with at least one customer. Customer partnership agreement signed WP4
Objective 5: Communication & Commercialisation
Sub-objective 5.1: New Customer Sign-up Dissemination and communication of the project, and the technology through the relevant channels. Additional customer sign-up WP6
Sub-objective 5.2: Business Plan Based on the project a new investor-ready business plan will be prepared. Business Plan complete WP5
Sub-objective 5.3: Secure Investment Throughout the course of the project we will engage with relevant investors, both strategic and institutional. Investment secured for PICOMB go-to-market phase WP5

 

Having achieved these objectives, beyond this SME Instrument Phase 2 project we envisage a further phase which will focus on full market entry. This will be achieved via private rather than public co-funding.